Agreement for the supply and installation of electrical systems for emergency maintenance due to rainwater at the University of Bahrain To avoid recurrence of the problem in the future For the safety of the University of Bahrain members So that the quality of safety is maintained always
Mandatory Requirements:· Bidders who are not EWA-Certified will be disqualified.
· All site workers who will need to enter the substations must have approval from EWA to work in substations with High-Voltages (11 KV) equipment. Failure to provide such approvals will disqualify the bidding company.
· Bidders using Electrical parts that do not comply with the Electrical Standards In terms of standards and quality specifications set by EWA and/or the Ministry of Works will be disqualified.
· Any bid with a delivery time (both parts and labor) exceeding 16 weeks will be excluded from the tender.
الشروط الإلزامية:
1. سيتم استبعاد عروض الشركات غير المعتمدة من قبل هيئة الكهرباء والماء.
2. سيتم استبعاد عروض الشركات التي لا تقدم ما يثبت اعتمادا من قبل هيئة الكهرباء والماء للعمل داخل المحطات الفرعية ذات الجهد العالي (11 كيلوفولت) للعمال الذين سيعملون داخل المحطات الفرعية بجامعة البحرين.
3. سيتم استبعاد العروض المدرج فيها معدات كهربائية غير متطابقة مع المواصفات الكهربائية المعتمدة من حيث مواصفات المعايير والجودة من قبل هيئة الكهرباء والماء و وزارة الأشغال.
4. سيتم استبعاد أي عطاء يتجاوز وقت التسليم (الأجزاء والعمالة) 16 أسبوعًا من المناقصة.